The maintenance dredging of Zhenjiang Seagoing Vessel Anchorage will soon be carried out. To ensure safe mooring, the construction unit will carry out construction by zonal and time-phased method. The total construction period is 125 days, and the project is expected to be completed by the end of November 2026.
Vessels passing by and seagoing ships intending to moor at this anchorage are requested to closely follow the operation progress and comply with relevant navigation requirements.
The Zhenjiang Seagoing Vessel Anchorage will be divided into two construction areas:

| Area | Location | Construction Period |
|---|---|---|
| Dredging Area No.1 | Upstream | April – May |
| Dredging Area No.2 | Downstream | October – November |
During construction in No.1 Dredging Area, No.2 Dredging Area will function normally as an anchorage.

During construction in No.2 Dredging Area, No.1 Dredging Area will function normally as an anchorage.
During construction, the construction area will be under closed management. Any non-construction vessels are prohibited from entering. The non-construction area remains in normal anchorage service.
A 13m3 Grabd Dredger from Zhenjiang Yanyang Engineering Co., Ltd will participate in the projects.